Generator transfer switches and backfeeding
Short answer: Never power house wiring by plugging a generator into a wall outlet ("backfeeding"). It can electrocute utility workers and neighbors served by the same transformer (CPSC). To run house circuits on a generator, have a qualified electrician install it with a transfer switch (OSHA). In Florida that is electrical contracting: hire a licensed electrical contractor and get the permit first (§ 489.531).
What backfeeding is and why it's dangerous
CPSC: trying to power house wiring by plugging the generator into a wall outlet is "extremely dangerous," presents an electrocution risk to utility workers and neighbors served by the same utility transformer, and bypasses some built-in household circuit protection (CPSC Safety Alert).
OSHA: attaching a generator directly to a building's electrical system without a properly installed transfer switch can energize wiring systems for great distances, which puts utility workers and others at risk (OSHA 3286).
What a transfer switch is for
A transfer switch is the device OSHA names for connecting a generator to a building's electrical system. OSHA's rule: no direct connection unless a qualified electrician has properly installed the generator with a transfer switch, because without one the generator can energize wiring systems for great distances (OSHA 3286). Which type of switch fits your panel and generator is a question for a licensed electrical contractor and your building department.
Who may install one in Florida
- Installing or altering wiring and apparatus that generate or use electrical energy is electrical contracting (§ 489.505(12)). Only certified or registered contractors may do it for pay (§ 489.531(1)(a)).
- A residential electrical specialty license covers qualifying 1 to 4 family homes up to 2 stories, single-phase up to 400 amps (R. 61G6-7.001(3)).
- Homeowners may act as their own electrical contractor on their own single-family home or duplex for their own use, but must personally sign the permit application and may not hire an unlicensed person (§ 489.503(6)).
- Work needing a permit can't start until the permit is in effect (§ 489.531(1)(i)).
Codes
The Florida Building Code applies statewide and is updated every 3 years from model codes that include the National Electrical Code (§ 553.73(6)-(7)). Your building department inspects the work.